Client: Bloor Homes, Western . Total build of 600 2, 3, and 4 bed homes.
Brief description of work being carried out by Bell Contracting;
Infrastructure onsite; mains foul and storm drainage which flows for over 6000m beneath the roads and ground.
Mains water, mains electric, mains gas and BT direct fibre this has been laid in a combined service trenches stretching over 2000m which runs along roads which flows for nearly 3km through the site and joins the A49 and Roman Road. Together , this has been installed over the last 13 months alongside handing over 113 Stage1 plots and 71 plots being finished on time and ready for CML sign off .
This beautiful site is surrounded by green open space in the stunning Herefordshire surroundings.